Construction
How often should a construction site be flown for progress documentation?
3 min read
A single aerial photo of a job site is a nice picture. A series of them, taken the same way on a regular schedule, is a record. It shows what was built, when, and in what order, and it settles a lot of questions later that nobody thought to ask at the time.
The value is in the schedule and the consistency, not in any one flight. Here is how to set both.
Tie the schedule to how the project is managed
There is no one right interval. The right one is whatever lines up with the way the project is already tracked and paid.
- Monthly works for a lot of projects, especially when flights line up with monthly progress meetings or pay applications. Owners and lenders get a current view of the site at the same point every month.
- Every two weeks or weekly makes sense during fast-moving phases: site work, foundations, structural steel, anything where a lot changes between meetings.
- At milestones, in addition to the regular schedule: before and after major pours, at substantial completion, and before anything gets covered up that someone may later want to see.
A common pattern is a steady monthly flight with extra flights added around the phases that move fastest. Decide it at the start, so the record has no gaps.
Make every flight comparable
A progress record is only useful if this month can be laid next to last month. That means flying the same way every time:
- The same flight path and altitude, so the site-wide view lines up from one flight to the next.
- The same fixed viewpoints for oblique shots, the angled views from the corners of the site where vertical progress shows clearly.
- The same deliverables each time, so nobody is comparing a map to a video.
Change the method halfway through and you can still see the site, but you lose the ability to compare it cleanly.
What each flight should capture
A solid progress flight usually includes:
- A site-wide overhead map, like an orthomosaic, that shows the whole site to scale. Our note on orthomosaic maps and 3D models explains the difference.
- Fixed-angle oblique photos from the same points every time.
- 4K video of the site, for presentations and for people who will never read a report.
- Volumes or elevations when they matter, for example earthwork or stockpiles during site work.
Every image is geo-tagged and dated, which is what turns a photo into documentation.
Who uses the record
- Owners and developers use it to see progress without driving to the site, and to share it with partners and lenders.
- Contractors use it to track the schedule, coordinate trades and show work completed.
- Engineers and architects use it to check what was built against what was designed.
- Insurance professionals and attorneys use it when a question comes up later about what was on site and when. A dated, geo-tagged aerial record is hard to argue with.
A note on safety and access
Commercial drone work in the United States requires an FAA Part 107 licensed pilot. Many job sites also have their own rules about when and where aircraft can fly, especially with cranes up and crews working. Agree on flight windows with the site superintendent at the start, and the schedule runs itself after that.
How we do it
We fly construction progress documentation, site surveys and volumetric measurements for contractors, owners and developers across Houston, Conroe, Montgomery, Magnolia and the DFW metroplex. We are FAA Part 107 licensed and fully insured, and our work has included documenting bridge construction like the project in the photo above. See our services, or request a quote with the site location, the project timeline and what you need the record for.